Phase 2 – building construction of the one-stop centre

One-Stop Centre Phase 2 – Building & Construction Work

15th May 2024 1st meeting with BMC Legend Builder Sdn Bhd at project site office

Building Construction 1

The project site now officially handed over to BMC Legend Builder Sdn Bhd

Building-Construction-2

27th May 2024 Ground beam work in progress

Building Construction 3

8th June 2024 Casting ground beam in progress

Building Construction 4

11th June 2024 Plumber start work at site

Building Construction 5

11th June 2024 Installed ground beam

Building Construction 6

19th June 2024 – OSD Compact Crusher Run

July-2024-29

25th  June 2024 – OSD

July-2024-28

27th June 2024 – Casting OSD Base

July-2024-27

29th June 2024 – Spray Anti-Termite

July-2024-26

29th June 2024 – Lay Damp Proof Membrane

July-2024-25

1st July 2024 – Lean Concrete Ground Floor Slab

July-2024-24

4th July 2024 – Casting Ground Floor Slab

July-2024-30

6th July 2024 – Casting of OSD

July-2024-23

6th July 2024 – Grouting at Pipe

July-2024-22

6th July 2024 – Column Formwork Start

July-2024-21

10th July 2024 – Column Reinforcement

July-2024-20

10th July 2024 – OSD

July-2024-19

15th July 2024 – Column Work in Progress

July-2024-18July-2024-31

2nd August 2024

Aug1

6th August 2024 – 1st Floor Work in Progress

Aug2

8th August 2024 – 1st Floor Slab RC Structure & Concreting

Aug3Aug4

13th August 2024 – 1st Floor RC Slabs & Beams Concreting

Aug5 Aug6

15 August 2024 – Water Curing Works

20240815-01 20240815-02

16th August 2024 – Water Curing Works

20240816-01

16th August 2024 – Formworks for Ramps

20240816-02

17th August 2024 – Site Safety Briefing

20240817-01

Work Progress from 17/8/24 – 14/9/2024

20240817-02 20240823 20240826 20240827-1 20240827-2 20240828 20240829 20240830 20240830-2

Work Progress from 1st September 2024 – 30th September 2024

20240902-1 20240902-2 20240903 20240904 20240905-1 20240905-2 20240907 20240909-1 20240909-2 20240909-3 20240911-1 20240911-2 20240912-1 20240912-2 20240914 20240918 20240923-1 20240923-2 20240924 20240928 20240930

Work progress from 1st October – 31st October 2024

20241002 20241007

9th October 2024 – Representatives from Jonaron Charitable Foundation visited One-Stop Centre project site

20241009 20241010 20241011-1 20241011-2 20241012 20241014 20241015 20241016-1 20241016-2 20241017 20241019 20241021 20241025 20241028

Work progress from 1st November – 30th November 2024

20241102-1 20241102-2 20241105 20241107 20241109-1 20241109-2 20241111-1 20241111-2 20241114 20241118 20241122 20241123 20241126 20241127 20241128

Work progress from 1st December – 31st  December 2024

20241203 20241205 20241206 20241209 20241212-1 20241212-2 20241212-3 20241213 20241217 20241218 20241219 20241220 20241223-1  20241224 20241226 20241227 20241228-1 20241228-2