One-Stop Centre Phase 2 – Building & Construction Work
15th May 2024 1st meeting with BMC Legend Builder Sdn Bhd at project site office
The project site now officially handed over to BMC Legend Builder Sdn Bhd
27th May 2024 Ground beam work in progress
8th June 2024 Casting ground beam in progress
11th June 2024 Plumber start work at site
11th June 2024 Installed ground beam
19th June 2024 – OSD Compact Crusher Run
25th June 2024 – OSD
27th June 2024 – Casting OSD Base
29th June 2024 – Spray Anti-Termite
29th June 2024 – Lay Damp Proof Membrane
1st July 2024 – Lean Concrete Ground Floor Slab
4th July 2024 – Casting Ground Floor Slab
6th July 2024 – Casting of OSD
6th July 2024 – Grouting at Pipe
6th July 2024 – Column Formwork Start
10th July 2024 – Column Reinforcement
10th July 2024 – OSD
15th July 2024 – Column Work in Progress
2nd August 2024
6th August 2024 – 1st Floor Work in Progress
8th August 2024 – 1st Floor Slab RC Structure & Concreting
13th August 2024 – 1st Floor RC Slabs & Beams Concreting