Phase 2 – building construction of the one-stop centre

One-Stop Centre Phase 2 – Building & Construction Work

15th May 2024 1st meeting with BMC Legend Builder Sdn Bhd at project site office

Building Construction 1

The project site now officially handed over to BMC Legend Builder Sdn Bhd

Building-Construction-2

27th May 2024 Ground beam work in progress

Building Construction 3

8th June 2024 Casting ground beam in progress

Building Construction 4

11th June 2024 Plumber start work at site

Building Construction 5

11th June 2024 Installed ground beam

Building Construction 6

19th June 2024 – OSD Compact Crusher Run

July-2024-29

25th  June 2024 – OSD

July-2024-28

27th June 2024 – Casting OSD Base

July-2024-27

29th June 2024 – Spray Anti-Termite

July-2024-26

29th June 2024 – Lay Damp Proof Membrane

July-2024-25

1st July 2024 – Lean Concrete Ground Floor Slab

July-2024-24

4th July 2024 – Casting Ground Floor Slab

July-2024-30

6th July 2024 – Casting of OSD

July-2024-23

6th July 2024 – Grouting at Pipe

July-2024-22

6th July 2024 – Column Formwork Start

July-2024-21

10th July 2024 – Column Reinforcement

July-2024-20

10th July 2024 – OSD

July-2024-19

15th July 2024 – Column Work in Progress

July-2024-18July-2024-31

2nd August 2024

Aug1

6th August 2024 – 1st Floor Work in Progress

Aug2

8th August 2024 – 1st Floor Slab RC Structure & Concreting

Aug3Aug4

13th August 2024 – 1st Floor RC Slabs & Beams Concreting

Aug5 Aug6